Public Works Update:

  • Sidewalk Projects
  • School Zone Signage
  • Clarks Run Cleanup at Michael Smith Park

Cemeteries Update:

  • Updated Rules & Regulations
  • Fee Schedule Changes
  • Capital Improvement Projects to be recommended in 2025/2026
  • Possible Expansions

Parks Masterplan Update:

  • Watch Update from Director of Parks & Recreation, Tommy Barton, from the same meeting
  • Recommendations from Danville-Boyle County Parks & Recreation Committee

Wayfinding Update:

  • New Downtown Directory signs to be installed at Weisiger Park & Constitution Square
  • In the process of reviewing designs for Welcome to Danville Signs
  • Pedestrian Wayfinding focus

Stormwater Update: 

  • Preparing to update Stormwater Manual
  • Twinbrook Culvert Replacement
  • Sub-Basin S Assessment

Streets & Sidewalks:

  • Baughman Avenue Sidewalk design is complete and approved, still on schedule for Spring 2025 start.
  • 2024 Paving List Completed

Trails:

  • Stanford Ave Pedestrian Refuge - more visibility features to be added
  • Woven Wire Mountain Bike Trail - signage coming soon

Other:
Traffic calming efforts, Downtown Masterplan, Planning & Zoning Comprehensive Plan, EDA KPDI Grant, Republic Downtown Garbage Collection