The construction on the new sidewalks and lighting downtown continues to progress. The Contractor has completed the installation of approximately 9' of the new sidewalk along the buildings on the south side of Main Street, and has begun the demolition of the old sidewalks and installation of electrical conduit on the north side of Main Street. Construction along the north side of Main Street will continue throughout the month of September.


The Contractor is maintaining access to all downtown businesses as much as possible and downtown businesses are remaining open throughout construction, so please visit them and support them during the construction disturbances. Efforts are being made to minimize the disruption to parking, and the Parking Garage will remain free for two hours throughout construction. Click here to view drone footage of the project.